Project Description

Here’s the latest going on with our construction project:

 

  • The chiller for the church has been relocated to the sacristy roof and is now operational.  Thanks for your patience while we went without air conditioning during that move.
  • Storm piping was put in place on the west side of the church
  • The drainage work in the southeast parking lot is done!  Thanks for your patience while that section of the parking lot was closed for the last four weeks.

 

Over the next couple of weeks:

  • Excavation will begin for a stairwell that will connect the new building to the Fr. Jones Room in the church basement, and work will begin on that point of connection.